Connections boost for small-scale renewables
Small-scale energy projects are to benefit from faster connections after Ofgem approved a key modification to the Connection and Use of System Code.
Small-scale energy projects are to benefit from faster connections after Ofgem approved a key modification to the Connection and Use of System Code.
Under the change, the threshold for requiring an Evaluation of Transmission Impact Assessment (TIA) in England and Wales increases from 1MW to 5MW,
While essential for larger projects, the TIA process often delayed smaller initiatives with minimal impact on the grid.
The system operator said the modification is especially beneficial for community energy projects, which often fall under the 5MW mark.
Although the new threshold does not affect Scottish projects, the National Energy System Operator said its broader package of connection reforms will benefit projects across Great Britain.